Start No Earlier Than

Constraint type that requires a task to start on or after a specific date.

Example

If Task A can only happen after the 4th of July Holiday, then you might apply a Start No Earlier Than constraint of July 5th. This way you know that the earliest this task will start is July 5th.

Calculation

N/A

Notes

Constraints and dependencies can be difficult to manage in large project plans. As a general rule of thumb dependencies should be used to drive start dates. In practice, however, this can create extremely complex plans that shift constantly. Understanding when to use a constraint versus a dependency can help save yourself a lot of hassle.